CONTENTS
1.0. SCOPE
2.0 RESPONSIBILITY
3.0 SAFETY
4.0 OIL FILLED DISTRIBUTION TRANSFORMER
TOOLS / EQUIPMENTS
TEST EQUIPMQNTS
INSTALLATION PROCEDURE
INSPECTION & TESTING PROCEDURE
TOOLS / EQUIPMENTS
· Hand tools for Electricians
· Lifting crane
· Fork Lift
TEST EQUIPMENT
· Digital multimeter.
· Ductor Tester
· Clamp on Ammeter (Digital)
· High pot Tester Set (with all accessories)
· 1 KV Insulation Resistance Tests
· 5 KV Insulation Resistance Tests
· Secondary injection set
· Phase rotation meter.
All the testing instruments will have calibration certificate valid for minimum six months. Calibration certificate can be verified during testing.
INSTALLATION PROCEDURE
· The Distribution Transformer will be installed in place after completion of all civil work in Transformer Room i.e. Concrete plinth, Trenches, Fence, channels external wall etc…
· Installation of the transformer will be co-ordinated with the civil team
· Rails for transformer rollers will be installed
· The transformers will be unloaded directly onto position as per approved Layout drawings.
· Align and level the transformers.
· Fix the transformer on the rail as per manufacture recommendation.
· Gladding and proper termination for HV side.
· Gladding and proper termination for
· Ground the transformer as per approved Earthling Layout
· Testing of the transformer as per Inspection and Testing procedure
· Termination of HV / LV Control and Instrument cables. Testing of HV cable shall be carried out after termination is installed and before the cable is finally bolted to the HV terminal of the transformer
· Installation shall be carried out fully complying with manufacturer’s recommendation and procedures.
· Installation check list will be submitted to Engineer for approval
· Tighten the bolts with torque wrench as per manufacturer recommendation
· Necessary site inspection requests shall be submitted to Engineer during the above activities at site.
· Maintenance procedure / Instructions shall be furnished to maintenance team / Engineer during delivery of materials at site.
INSPECTION OF TRANSFORMER
· Check Transformer for any Physical damage
· Check nameplate rating and tagging
· Check if installation is made as per approved drawing and in line with vendor recommendations
· Check Cable glanding and termination
· Check operation and condition of tapping switch
· Check Earthing
· Check Cable and Cable Tray supports
· Check protection devices i.e. winding temperature switch / thermometer
· Check door locks for HV and LV Terminal boxes
TESTING OF TRANSFORMER
The following Test of the Transformer will be carried out:
· Insulation Resistance winding
· Megger of winding HV side 5000V megger
· Measurement of winding resistance
· Measurement of impedance voltage on all tap’s
· Measurement of no load loss
· Measurement of load losses at principle tap and extremes
· Induced AC voltage withstand voltage test with measurement of partial discharge
· Separate source AC voltage withstand voltage test
· Measurement of Voltage ratio between primary and secondary winding
· Check operation of winding temperature switch / indicator
· Check vector group by voltmeter method
· Check phase sequence
· Check polarization index
· Applied over voltage test at 2000V, AC, 60 sec. on wiring and supervisory equipment
· Any other test as stated in ADDC Specs
No comments:
Post a Comment